PROGRESS OF WORKS AT NSOTOKA HCIII
The district leadership held a site meeting for the construction of HCIII in nsotoka parish Kayunga subcounty.
The scope of work comprised of constructing a general ward, out patients department, 4 stance latrine, placenta pit, medical waste pit and external works.
The project was constructed by the UPDF engineers brigade at a cost of 837,310,381 million shillings which was cleared.
The overall progress of the work stood at 99% and the project was ready for commissioning.